Which task dependency involves the successor not being able to start until the predecessor starts?

Prepare for the PMT 4910 Advanced Certification Exam. Utilize flashcards and multiple choice questions with hints and explanations. Gear up for your certification success!

Multiple Choice

Which task dependency involves the successor not being able to start until the predecessor starts?

Explanation:
Understanding how task dependencies control when a successor can begin relative to its predecessor is key. In a Start-to-Start relationship, the start of the successor is constrained by the start of the predecessor; the successor cannot begin until the predecessor has begun, though it may start at the same time or a bit later if a lag is used. This matches the scenario described where the successor’s start depends on the predecessor starting. If the dependency were Finish-to-Start, the successor would have to wait for the predecessor to finish before starting. If it were Finish-to-Finish, the constraint would apply to finishing times rather than starting. If it were Start-to-Finish, the finish of the successor would depend on the start of the predecessor, which is a different linkage. So the described condition aligns with a Start-to-Start dependency.

Understanding how task dependencies control when a successor can begin relative to its predecessor is key. In a Start-to-Start relationship, the start of the successor is constrained by the start of the predecessor; the successor cannot begin until the predecessor has begun, though it may start at the same time or a bit later if a lag is used. This matches the scenario described where the successor’s start depends on the predecessor starting.

If the dependency were Finish-to-Start, the successor would have to wait for the predecessor to finish before starting. If it were Finish-to-Finish, the constraint would apply to finishing times rather than starting. If it were Start-to-Finish, the finish of the successor would depend on the start of the predecessor, which is a different linkage.

So the described condition aligns with a Start-to-Start dependency.