Which term describes tasks that must be finished before another task can start?

Prepare for the PMT 4910 Advanced Certification Exam. Utilize flashcards and multiple choice questions with hints and explanations. Gear up for your certification success!

Multiple Choice

Which term describes tasks that must be finished before another task can start?

Explanation:
In project scheduling, tasks that must be finished before another can start are called the predecessor. This sets the sequence: the predecessor completes first, and the next task (the successor) can begin. The relationship is often finished-to-start, meaning the successor cannot start until the predecessor finishes. A milestone is simply a notable point or event, not a task dependency. A constraint is a limitation that affects scheduling but does not define a direct predecessor–successor link. For example, if Task A must be completed before Task B begins, Task A is the predecessor and Task B is the successor.

In project scheduling, tasks that must be finished before another can start are called the predecessor. This sets the sequence: the predecessor completes first, and the next task (the successor) can begin. The relationship is often finished-to-start, meaning the successor cannot start until the predecessor finishes. A milestone is simply a notable point or event, not a task dependency. A constraint is a limitation that affects scheduling but does not define a direct predecessor–successor link. For example, if Task A must be completed before Task B begins, Task A is the predecessor and Task B is the successor.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy